MonteCarloProject allows to set different dependency types between predecessors and successors.

Dependencies are set in the task display and they are always described from predecessor to successor. There are following dependency types (see picture 1):

  • Finish-to-start. Successor can be started when the predecessor is finished.
  • Start-to-start. Successor can be started when the predecessor is started.
  • Finish-to-finish. Successor can be finished when the predecessor is finished.
  • Start-to-finish. Successor can be finished when the predecessor is started.

montecarloproject task display and dependencies

Picture 1. Task display and dependencies.

Save
Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Marketing
Set of techniques which have for object the commercial strategy and in particular the market study.
Facebook
Accept
Decline
Google
Accept
Decline
Unknown
Unknown
Accept
Decline
Analytics
Tools used to analyze the data to measure the effectiveness of a website and to understand how it works.
Google Analytics
Accept
Decline